Colorado State Announces Timeline For Sonny Lubick Field At Hughes Stadium
7/14/2003 12:00:00 AM | Football
Fort Collins, Colo. - Colorado State University Interim Director of Athletics Christine Susemihl today outlined the timeline for the renovation and expansion of Sonny Lubick Field at Hughes Stadium.
The goal is to have the entire project completed prior to the beginning of the 2005 season, Susemihl said. The project will be broken down into various components to be completed during the next 24-26 months, beginning with an artificial practice field south of Moby Arena later this fall.
?We have worked diligently with the individuals on our campus and with the staff at HOK and Aller-Lingle about the entire project. We have broken down the project into specific segments that will completed in a timely fashion,? said Susemihl.
The timeline includes:
The expansion and renovation project was made possible by a $15.2 million gift provided by the Bohemian Foundation and president Pat Stryker. She made the presentation during a ceremony on May 14, 2003 in Fort Collins.
Susemihl said the athletics department continues to search for additional donors as a way of supplementing the program?s pursuit of excellence in all areas. Individuals interested in supporting student-athlete scholarships, endowments, facility upgrades or program enhancements can call the athletics department at 970-491-4666.